When building a project schedule, one of the most important steps is understanding how to calculate estimated project duration. While effort hours are often easy to estimate, converting those hours into a realistic schedule requires more analysis.
If every team member worked eight hours per day at full productivity, duration calculations would be simple. For example, an activity estimated at 80 effort hours with one full-time resource would take 10 days, calculated as 80 divided by 1 resource divided by 8 hours per day. Assigning four full-time resources would reduce the duration to 2.5 days.
In reality, productivity is rarely perfect. To produce more accurate schedules, effort hours must be adjusted to reflect on how work is performed.
Why Effort Hours Alone Are Not Enough
Effort hours represent the total amount of work required, but they do not account for productivity loss, availability, or scheduling constraints. Estimating project duration accurately requires converting effort into duration using realistic assumptions.
The following seven steps provide a structured approach to calculating estimated project duration more effectively.
7 Steps to Calculate Estimated Project Duration
1. Estimate Productive Hours Per Day
The first step is determining how many productive hours you can reasonably expect from each resource per day. While a standard workday may be eight hours, not all of that time is spent on focused project work.
Using an average of 6.5 productive hours per day helps account for meetings, coordination time, administrative tasks, and other unavoidable interruptions.
2. Determine the Number of Resources Assigned
Adding more resources can reduce duration, but not always in direct proportion. Two people may complete an activity faster than one, but not necessarily in half the time. Additional resources often introduce coordination overhead and diminishing returns.
At a certain point, adding more people may no longer shorten the schedule and can even increase duration.
3. Factor in Available Workdays
Known non-working time such as holidays, vacations, and training should be included in duration calculations. Unlike daily productivity loss, this time can usually be planned in advance.
Accounting for known absences improves schedule accuracy, especially on longer projects where availability varies across team members.
4. Account for Part-Time Resource Allocation
Not all resources are assigned full time. If a resource is only available part time, the activity duration must be adjusted accordingly.
For example, a 40-hour activity assigned to a resource available 25 percent of the time will take at least four weeks to complete. Partial allocation significantly affects estimated project duration and must be reflected in the schedule.
5. Include Delays and Lag Time
Some activities require minimal effort but still have long durations due to waiting periods. Examples include reviews, approvals, or external dependencies.
A task may only require one hour of effort but scheduling that effort may take days or weeks. These delays must be included when estimating duration.
6. Identify Resource Constraints
During initial scheduling, some activities may appear to be eligible for parallel execution. However, parallel work is only possible if the required skills are available at the same time.
If only one person has the skills needed for multiple activities, those activities may need to be performed sequentially, even if other resources are available.
7. Document All Assumptions
No project estimate is created with complete information. Documenting assumptions is critical for transparency and future adjustment.
Recording assumptions related to productivity, availability, constraints, and dependencies allows stakeholders to understand how the estimated project duration was determined and supports better decision-making when conditions change.
Why Accurate Duration Estimates Matter
Accurate duration estimates improve schedule reliability, resource planning, and stakeholder confidence. By accounting for productivity, availability, and constraints, project managers can create schedules that better reflect real-world conditions.
Using a structured approach to estimating duration helps reduce surprises and supports more effective project execution.
Key Takeaways
- Effort hours must be converted into realistic durations
- Productivity varies and should be estimated conservatively
- Resource availability directly impacts schedule length
- Delays and constraints must be included in duration estimates
- Documenting assumptions improves transparency and flexibility


